Project Background
The accelerated popularization and global layout of new energy vehicles in China are reshaping the global transportation ecosystem and leading the transformation of travel modes worldwide. To promote the overseas lithium battery market, Foshan Shuochen launched a 4m³ lithium-ion battery anode material coating and granulation equipment for overseas clients. This equipment has obtained CE certification with guaranteed safety performance.
Project Overview
Raw Materials: Pitch and Coke
Project locations
Norway
Project Requirements
1.Automatic production line;
2.daily output of 4.3 tons per single set of equipment;
3.target particle size of approximately 16μm
Customized Project Solution
Considering the differences between overseas mechanical equipment standards and domestic standards, we provide the following customized solutions exclusively for overseas clients:
1. Supply 4m³ lithium-ion battery anode material coating granulation equipment fully compliant with EU Machinery Directive (2006/42/EC), Low Voltage Directive (2014/35/EU), EMC Electromagnetic Compatibility Directive (2014/30/EU), with officially approved CE certification completed.
2. The electrical system of the equipment strictly complies with Norwegian national standards.
3. Labels and safety markings on the equipment body and auxiliary components adopt Norwegian (primary) + English (secondary).
4. Pipeline design fully adapts to on-site working conditions of Norwegian factories and complies with local industrial installation specifications.
5. Supporting waste gas treatment equipment meets the emission standards of the Norwegian Environment Agency (Miljødirektoratet).
6. Fully abide by Norwegian environmental protection regulations as well as EU RoHS and REACH standards.
Implementation & Delivery Process
1. Clarify the client’s project requirements and process design through 2 months of online email communication and offline meetings.
2. Complete the design and revision of project drawings via 2 months of online technical meetings.
3. Procure raw materials and conduct equipment manufacturing & processing for 4 months.
4. Complete customs declaration and international transportation within 1 month.
Project Achievements
1. The equipment has been highly recognized by the client with positive feedback and suggestions received.
2. Labor cost reduced by 16%; single batch production time per equipment shortened by 22% compared with domestic standard equipment.
3. finished product qualification rate reaches 91%